Scope of work
Transport and install one government-furnished single CXT concrete vault toilet from the Forest Service warehouse in Austin to Pine Creek Campground near Round Mountain, Nevada. Base work includes excavation, backfill, grading and installation. Option 1 removes the existing toilet, fills the opening and restores contours. The campground remains open during work. The anticipated start is July 2027, with 30 days after notice to proceed.
Opportunity details
- Issuing agency
- USDA Forest Service
- Location
- Sparks, Nevada
- Category
- Construction & infrastructure
- Notice type
- Combined Synopsis/Solicitation
- Published
- Oct 21, 2026
- Source status
- Published latest notice, not cancelled or archived
Documents & addenda
- C04 127EAX27Q0009 1442 with Clauses and Provisions Revised.pdfAccess checked Oct 28, 2026, 1:53 PM UTCSource file
- C04 Attachment 1 Schedule of Items.xlsxAccess checked Oct 28, 2026, 1:53 PM UTCSource file
- C04 Attachment 2 Statement of Work and Specification.docxAccess checked Oct 28, 2026, 1:53 PM UTCSource file
- C04 Attachment 3 Combined Maps Revised.pdfAccess checked Oct 28, 2026, 1:53 PM UTCSource file
- C04 Attachment 4 Wage Determination NV2026-0074 07-30-2026 Heavy Nye County NV.txtAccess checked Oct 28, 2026, 1:53 PM UTCSource file
Source notes
- The base item installs a government-furnished unit; existing toilet removal is Option 1. All items must be priced for evaluation.
- SAM lists the Sparks office as the place of performance; the controlling statement of work and maps locate construction at Pine Creek Campground near Round Mountain.
- Specification 133450 mentions a 2-inch leveling course and a 6-inch gravel base in different subsections. Confirm the layer interpretation before pricing; the directory does not prescribe a foundation design.