Needs a fresh source checkCombined Synopsis/SolicitationBid 1240LT26Q0109

4 GAOA Flaming Gorge Water System Buckboard in Ashley NF, Wyoming

USDA Forest Service · Wyoming

Needs a fresh source check. This record remains available for reference. Use the official notice to confirm its current status.

Scope of work

Reconstruct the Buckboard Marina raw-water intake and irrigation infrastructure in Ashley National Forest, Sweetwater County, Wyoming. Base work includes intake drilling and cofferdam work, pumps and pumphouse, raw-water pipeline/storage, access road, power and communications, and design/build electrical and SCADA systems. Five separately identified options cover finished-water storage tanks, looped distribution, water meters, a 40-GPM treatment-plant upgrade, and a waterline extension to a future dock. This is a total small-business set-aside with active SAM registration required. Use Amendment 0003 and its revised scope, specifications and Schedule of Items, and acknowledge all amendments with the quote.

Opportunity details

Issuing agency
USDA Forest Service
Location
Mc Kinnon, Wyoming
Category
Construction & infrastructure
Notice type
Combined Synopsis/Solicitation
Published
Oct 21, 2026
Source status
Published latest notice, not cancelled or archived

Documents & addenda

Source notes

  • Total Small Business Set-Aside; NAICS 237110. The solicitation states a $45 million small-business size standard and estimated construction magnitude $1 million-$5 million. Active SAM registration is required to submit a quote.
  • Bid guarantee of 20 percent of bid price, performance/payment bonds, and the attached Davis-Bacon wage determination apply. Submit the required signed offer, revised pricing schedule, technical/past-performance proposal and bid-guarantee documentation.
  • The organized site visit occurred September 24, 2026 at 1:00 PM Mountain Time. The reviewed documents do not state that pre-bid attendance was mandatory.
  • Amendment 0003 supersedes prior response dates with November 17, 2026. Use the revised SOW, specifications, measurement/payment documents, Schedule of Items and options supplement; the old SOI is deleted on SAM.
  • The October 21 RFI package states USACE permitting was still in progress and provides a stated bid basis for cofferdam/reservoir conditions. Do not interpret document capture as confirmation that construction permits have been issued.